Power Projects
Ava contracts with energy developers to build renewable power plants to supply our customers. We’re constantly expanding our portfolio of projects to meet our goal of 100% carbon-free electricity for all customers by 2030.
27
projects
1,495
MW of wind, solar, and geothermal
957
MW of storage
Energy services data as of 11/30/2025. Community investment data is updated semi-annually. These numbers are estimates.
Contracted Projects
Wind
Scott Haggerty Wind Energy Center
Alameda County
Online Jul 2020 |
20-year term
Greenbacker Capital
Nameplate MW: 54.8
Storage MW/MWh: 0
Solar
Golden Fields Solar
Kern County
Online Dec 2020 |
15-year term
Clearway Energy Group
Nameplate MW: 112
Storage MW/MWh: 0
Wind
Tecolote Wind
Torrance and Guadalupe (NM)
Online Dec 2021 |
10-year term
Pattern Energy
Nameplate MW: 100
Storage MW/MWh: 0
Storage
Henrietta D Energy Storage
Kings County
Online Dec 2021 |
15-year term
Convergent Energy and Power
Storage MW/MWh: 10/40
Solar
Tulare Solar Center
Tulare County
Online Apr 2022 |
18-year term
Idemitsu Renewables
Nameplate MW: 56
Storage MW/MWh: 0
Solar + Storage
Daggett 3
San Bernardino County
Online Sep 2023 |
15-year term
Clearway Energy Group
Nameplate MW: 50
Storage MW/MWh: 12.5/50
Solar + Storage
Oberon
Riverside County
Online Jan 2024 |
10+-year term
Intersect Power
Nameplate MW: 125
Storage MW/MWh: 125/500
Solar + Storage
Scarlet I
Fresno County
Online May 2024 |
20-year term
EDP Renewables North America
Nameplate MW: 100
Storage MW/MWh: 30/120
Storage
Tumbleweed Energy Storage
Kern County
Online Jul 2024 |
15-year term
REV Renewables
Storage MW/MWh: 50/200
Storage
Kola Energy Storage II
San Joaquin County
Online Aug 2025 |
20-year term
NextEra
Storage MW/MWh: 125/500
Solar
Oakland 1
Alameda County
Online Q4 2025 |
20-year term
Prologis
Nameplate MW: 0.72
Storage MW/MWh: 0
Solar
San Leandro 10
Alameda County
Online Q2 2026 |
15-year term
Prologis
Nameplate MW: 1
Storage MW/MWh: 0
Solar
Hayward Commerce
Alameda County
Online Q2 2026 |
15-year term
Prologis
Nameplate MW: 0.56
Storage MW/MWh: 0
Solar
Tracy 12
San Joaquin County
Online Q2 2026 |
20-year term
Prologis
Nameplate MW: 3
Storage MW/MWh: 0
Solar
Tracy 2 West
San Joaquin County
Online Q2 2026 |
20-year term
Prologis
Nameplate MW: 2
Storage MW/MWh: 0
Solar + Storage
Sun Pond
Maricopa County (AZ)
Online Q2 2026 |
20-year term
Longroad Energy
Nameplate MW: 42.5
Storage MW/MWh: 42.5/170
Wind
SunZia South
Lincoln County (NM)
Online Q3 2026 |
15-year term
Pattern Energy
Nameplate MW: 175.4
Storage MW/MWh: 0
Wind
SunZia North
San Miguel County (NM)
Online Q3 2026 |
15-year term
Pattern Energy
Nameplate MW: 74.6
Storage MW/MWh: 0
Solar
IP Easley I
Riverside County
Online Q1 2027 |
10-year term
Intersect Power
Nameplate MW: 75
Storage MW/MWh: 0
Solar
IP Easley II
Riverside County
Online Q1 2027 |
10-year term
Intersect Power
Nameplate MW: 75
Storage MW/MWh: 0